Article 16.64
in forceProcedures · De omgevingsvergunning
The competent authority shall decide on the application for an environmental permit within eight weeks or, if the intended decision on the application requires consent as referred to in Article 16.16, within twelve weeks after receipt of the application.
The competent authority may extend the decision periods referred to in the first paragraph once by a maximum of six weeks. This decision shall be made public within the decision period.
Simultaneously with or as soon as possible after the notification of the decision on the application for an environmental permit, the competent authority shall give notice of that decision in the manner determined in Article 12 of the Publication Act (Bekendmakingswet).
Pursuant to Article 28, paragraph 1, final sentence, of the Services Act, Section 4.1.3.3 of the General Administrative Law Act does not apply to the preparation of the decision on the application.
Het bevoegd gezag beslist op de aanvraag om een omgevingsvergunning binnen acht weken of, als de voorgenomen beslissing op de aanvraag instemming als bedoeld in artikel 16.16 behoeft, binnen twaalf weken na ontvangst van de aanvraag.
Het bevoegd gezag kan de beslistermijnen, bedoeld in het eerste lid, eenmaal met ten hoogste zes weken verlengen. Dit besluit wordt bekendgemaakt binnen de beslistermijn.
Tegelijkertijd met of zo spoedig mogelijk na de bekendmaking van de beslissing op de aanvraag om een omgevingsvergunning geeft het bevoegd gezag kennis van dat besluit op de in artikel 12 van de Bekendmakingswet bepaalde wijze.
Met toepassing van artikel 28, eerste lid, laatste zinsnede, van de Dienstenwet is paragraaf 4.1.3.3 van de Algemene wet bestuursrecht niet van toepassing op de voorbereiding van de beslissing op de aanvraag.