1.

If no objections to the expropriation order have been submitted, the court shall, within six months after the expiry of the period referred to in Article 16.98, paragraph 1, render a decision on the petition for confirmation.

2.

If objections to the expropriation order have been submitted, the court shall render a decision on the petition for confirmation within six months after receipt of the response to the objections, as referred to in Article 16.99, paragraph 1.

3.

If, pursuant to Article 8:51a or 8:51d of the General Administrative Law Act, application is made, the court shall, by way of derogation from the first or second paragraph:

a.

within six months after receipt of the response to the objections an interim decision, and

b.

within six months after the dispatch of the interlocutory decision, a final decision.

1.

Als er geen bedenkingen tegen de onteigeningsbeschikking zijn ingebracht, doet de rechtbank binnen zes maanden na afloop van de termijn, bedoeld in artikel 16.98, eerste lid, uitspraak op het verzoek tot bekrachtiging.

2.

Als er bedenkingen tegen de onteigeningsbeschikking zijn ingebracht, doet de rechtbank binnen zes maanden na ontvangst van de reactie op de bedenkingen, bedoeld in artikel 16.99, eerste lid, uitspraak op het verzoek tot bekrachtiging.

3.

Als krachtens artikel 16.113artikel 8:51a of 8:51d van de Algemene wet bestuursrecht wordt toegepast, doet de rechtbank in afwijking van het eerste of tweede lid:

a.

binnen zes maanden na ontvangst van de reactie op de bedenkingen een tussenuitspraak, en

b.

binnen zes maanden na verzending van de tussenuitspraak een einduitspraak.